The right method depends on your source system: for Exchange Server, cutover or hybrid may fit depending on version and size, while Google Workspace and hosted Exchange need their own paths. We plan Exchange Online migrations in seven phases, from discovery to decommissioning. With CNEXT, a full migration for an SME with 80 employees typically costs CHF 25,000–45,000 including training.
For many organisations, Exchange Online is the way into Microsoft 365. The steps below apply to moving from an on-premises Exchange Server, from Google Workspace or from a hosted Exchange provider.
Why switch now?
Microsoft ended support for Exchange Server 2016 and 2019 on 14 October 2025. Exchange Server Subscription Edition is available, but in our view it does not make economic sense for most SMEs. The case for Exchange Online:
- Mailboxes can be stored in Swiss data centres (Zurich and Geneva); see our article on Microsoft 365 data residency for details
- no server of your own, no patching, no tape library for backups
- integration with Microsoft Teams, SharePoint and Microsoft 365 Copilot
- protection against phishing and malware with Microsoft Defender for Office 365
- mailboxes of 50 to 100 GB per person, depending on the licence
Which method fits?
| Method | Suitable for | Effort | Duration |
|---|---|---|---|
| Cutover | SMEs with up to around 150 mailboxes, source system Exchange 2013 or later | low | 1–2 weekends |
| Staged | 150–2,000 mailboxes on Exchange 2003/2007 | medium | 4–12 weeks |
| Hybrid (Modern Hybrid) | Corporate groups, gradual coexistence, GAL sync | high | 3–9 months |
| IMAP/PST | Hosted Exchange, Notes, GroupWise | medium | 2–8 weeks |
| Google Workspace | Gmail and Google Workspace | medium | 4–10 weeks |
Microsoft says a staged migration is intended for Exchange 2003/2007, not for Exchange 2010 or 2013. For most SMEs with 30–200 employees, cutover or Modern Hybrid with express migration is the pragmatic route.
The seven phases
1. Discovery and assessment (1–2 weeks)
- Inventory of all mailboxes: user, shared and resource mailboxes, distribution lists, public folders, archives
- Mailbox sizes, attachment statistics, retention
- Mail flow: MX records, SPF, DKIM, DMARC and upstream anti-spam gateways such as Hornetsecurity or Proofpoint
- Third-party systems that send via SMTP: ERP systems such as Bexio or Abacus, scanners, IoT devices, newsletter tools
- Mobile devices: ActiveSync, Outlook on the web, Outlook for iOS and Android
2. Tenant preparation (1 week)
- Check the tenant's default geography (Switzerland) and document data residency for each service
- Verify and configure domains: TXT, MX, Autodiscover, SPF, DKIM, DMARC
- Prepare licences: Business Standard, Business Premium or E3/E5
- Harden Microsoft Entra ID and set up Conditional Access
- Policies for Microsoft Defender for Office 365: Safe Links, Safe Attachments, anti-phishing
3. Identity and synchronisation (1–2 weeks)
- Entra Connect or Cloud Sync for hybrid identities
- optionally pass-through authentication or password hash sync
- Multi-factor authentication (MFA) for all users
- Privileged Identity Management (PIM) for admin roles
4. Pilot (1–2 weeks)
- 5–15 pilot mailboxes from IT, management and one pilot department
- Test Outlook profiles, mobile devices, signatures, DNS, permissions and delivery in both directions
- Document the results and update the runbook
5. Wave planning and migration (2–8 weeks)
- Waves of 50–150 mailboxes, typically over weekends
- Tools: Exchange Online migration endpoints or BitTitan MigrationWiz
- Communication to employees: what changes, and when are the maintenance windows?
- Monitor throttling, bandwidth and error reports
- Plan the rollback
6. Cutover and mail flow switch (1 weekend)
- Switch the MX record to Exchange Online or to the mail gateway
- Reconfigure the anti-spam gateway or replace it with Defender for Office 365
- Move third-party systems to SMTP AUTH or High Volume Email for Microsoft 365
- Test all inbound and outbound scenarios
7. Post-migration and decommissioning (2–4 weeks)
- Migrate public folders to Microsoft 365 Groups or SharePoint
- Decommission the old Exchange servers and remove the hybrid configuration cleanly; with an on-premises identity source, follow Microsoft's guidance on decommissioning on-premises Exchange servers
- Configure retention policies and litigation hold
- Set up backup with Microsoft 365 Backup, Veeam or mount10
- Training for Outlook on the web, the new Outlook and mobile devices
Migrating from Google Workspace
This path is common for start-ups and for subsidiaries of international companies:
- Migrate mail, calendars and contacts through the Google Workspace (Gmail) migration endpoint
- Plan mail flow for the coexistence period
- Migrate Google Drive to OneDrive in parallel with ShareGate
- Move Google Groups to Microsoft 365 Groups
- Switch DNS and train employees on Outlook and Teams, which replace Gmail and Meet
Migrating from hosted Exchange
For example from Swiss providers, GoDaddy or Rackspace:
- IMAP migration for mail content only
- PST export and import for historical data
- with Swiss providers, a direct cutover is often possible
- export calendars and contacts separately
Data residency, retention and the FADP
- Check data residency for each service and data category; the tenant location alone is not a complete answer.
- Review the data processing agreement (DPA) with Microsoft and file it.
- Enable sensitivity labels and DLP for email, for example to protect AHV (Swiss social security) numbers, IBANs or credit card data.
- Set retention policies for emails that fall under the ten-year retention obligation of Art. 958f of the Swiss Code of Obligations.
- Keep a record of processing activities under Art. 12 of the Swiss Federal Act on Data Protection (FADP).
Frequently asked questions
How long does the migration take for an SME with 80 employees? We typically plan around 2 weeks of discovery, 1 week of tenant set-up, 1 week of pilot, 2–4 weeks of migration in waves and 1–2 weeks of post-migration work.
Can we keep working during the migration? Yes, as a rule. The waves run over weekends, and with hybrid both systems stay in operation side by side during the migration.
What happens to public folders? They are either migrated directly to Exchange Online or moved to SharePoint Online or Microsoft 365 Groups. The latter is usually the more sustainable option.
Do we need an additional backup during the migration? We recommend a snapshot before the cutover. After that, an ongoing backup for Microsoft 365 should be in place: natively with Microsoft 365 Backup, with Veeam or with mount10.
What does a migration with CNEXT cost? Discovery from CHF 5,000, pilot migration from CHF 8,000. A full migration for an SME with 80 employees typically costs CHF 25,000–45,000 including training. We quote hybrid projects for corporate groups individually.
What to bear in mind
Durations and prices are typical values. In each case, the effort depends mainly on the number of mailboxes, the source system and the connected third-party systems.
As a Microsoft partner based in Bern, we carry out cutover, staged, hybrid and Google Workspace migrations.